Negative slack indicates a lack of slack over the entire project and the amount of time Group of answer choices an activity must be accelerated to complete the project by the required completion time. each activity on the critical must be accelerated to complete the project by the required completion time. all activities in the project must be accelerated to complete the project by the required completion time. an activity must be delayed to complete the project by the required completion time.